View cost variances

You can view cost variances per task, per resource or per project against a saved baseline.

View cost variances per task
  1. In iTaskX Pro choose „Task Sheet” > „Cost Table” in the „Views” toolbar icon. With iTaskX Standard choose „Gantt Chart” > „Cost Table” in the „Views” toolbar icon.
  2. Review the variance fields.

Note
The values for „Baseline Cost” 1 -10 are only available in the different columns which you can add to your view. For example „Baseline Cost 1”, „Baseline Cost 2”, „Baseline Cost 3”, „Baseline Cost 4”... . To add columns to your view, choose „Views” > „Edit Columns...” in the menu bar.

View cost variances per resource
  1. Choose „Resource Sheet” > „Cost Table” in the „Views” toolbar icon.
  2. Review the variance fields.
View project cost variances
  1. In iTaskX Pro choose „Task Sheet” > „Cost Table” in the „Views” toolbar icon. With iTaskX Standard choose „Gantt Chart” > „Cost Table” in the „Views” toolbar icon.
  2. In the „View Options and Styles” window Format Window activate the „Show Project Summary” check box.
  3. Review the variance fields in the „Project Summary” row.

Note

  • To review cost variances in a timeframe like days, weeks, quarters or year, choose the „Gantt Chart” in the „Views” toolbar icon, open the „Graph” area with the „Layout” Layout toolbar icon. After that add a summary graph by pressing the „+” button under the „Graph” area. In the upcoming pop-over choose the „Cost” value and add a second value „Base Cost”.